Production of Modules for a 3 Module test beam (Saphir)

In 2012 we started the production of a new set of modules, code named Saphir, integrating some modification in respect with the 2011 model (Korund), with the goal to perform a 3-Module test in Summer 2012. To achieve this goal we need to produce the following items:

Improvements from the previous model

Compared to the 2011 (Korund) module it will be necessary to improve on the following points:

Production tasks

The following tasks and related deadlines have been identified to be able to perform a test beam by (roughly) July 2012

Task

Deadline

Person in charge

Status

Backframe Production

End of April 2012

Robert

material ordered, CAD model updated (chamfer included)

HV Cables and connectors

End of April 2012

Felix

Connectors arrived

New PCB

End of April 2012

Felix

GEM Production

End of February 2012

Stefano

GEM Delivered. COMPLETED

GEM basic testing

Mid April 2012

Ceramic Frames Production

Mid April 2012

Stefano

Tooling for Gluing

Mid April 2012

GEM gluing

End of April /Mid May 2012

HV Test box improvement

End of March 2012

Robert

Solution for the distortion reduction

Meetings, minutes and reports

* Minutes of the brainstorming meeting concerning the backframe and the HV connectors


CategoryTpc

ThreeModuleProduction (last edited 2012-03-14 16:15:31 by StefanoCaiazza)